RobS Posted April 23, 2020 Report Share Posted April 23, 2020 Hello, Can System unavailability or downtime be factored into the simulation as a % say 1%. If so where can I input this figure please? Thanks, Rob Quote Link to comment Share on other sites More sharing options...
developer_fw Posted April 23, 2020 Report Share Posted April 23, 2020 Hi RobS, Since there are so many unknowns as to what the 1% refers to or for what period of time it applies, we do not currently offer this setting at the moment. After exporting the simulation results you can apply a factor as you wish, though. Or apply a maintenance period e.g. You can find the data export on the page "Presentation". Best regards, Frederik Quote Link to comment Share on other sites More sharing options...