Sandeep Singh Posted February 19, 2019 Report Posted February 19, 2019 I was designing Ground Mounted 100 MW Solar Power Plant in 2D. But system is not accepting 50,000.00kWp. System is asking me to enter the value in between 0 to 35,000. Quote
developer_mm Posted February 19, 2019 Report Posted February 19, 2019 Hi Sandeep Singh, there is a restriction in PV*SOL that you can only add 100000 modules per module area. In your case, simply create more module areas with the same modules and you should be fine. Kind regards, Marcel Quote