Rohith Posted February 27 Report Posted February 27 Hi, Is there a way to limit the grid export? for example in this project i want my own consumption to be at 25000 kWh/year and the excess to be sent to the grid. can you please tell me how to do it. Thanks in Advance Regards Rohith Quote
developer_fw Posted February 28 Report Posted February 28 Hello Rohith 22 hours ago, Rohith said: for example in this project i want my own consumption to be at 25000 kWh/year and the excess to be sent to the grid. can you please tell me how to do it. Could you elaborate on what might be your approach to achieve this? You might shift your consumption to hours of production of you PV system (adaptive consumers e.g.) shift the production of your PV system into hours of consumption (battery) Kind regards Frederik Quote