Start of operation


Venco Gary

Recommended Posts

PV CD -315kWp.pvprjHello, In this file, I set operation time to 2023/1/1,which is Sunday. And i set no consumption at weekends. But i checked the hourly values , there was still consumption on that day. The table shows that there was no consumption on January 3rd and 4th.  There should be a problem with the setup. Please help to check.  

image.jpeg

2023-04-06_171210.jpg

PV CD -315kWp.csv

Link to comment
Share on other sites

Hi Venco Gary,

the date of the start of operation is not considered in the simulation, only in the economic calculation (for the tariffs for example). The reference date for the load profiles is arbitrary and set to 01. January 2015 internally. So the first day of your load profile will always be a Thursday, if you choose to "Define Load Profile" like you showed above.

Hope that helps, kind regards,

Martin

Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.
Note: Your post will require moderator approval before it will be visible.

Guest
Unfortunately, your content contains terms that we do not allow. Please edit your content to remove the highlighted words below.
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

×
×
  • Create New...