Hello.

 

In my country, under net-metering scheme, the PV power that is not consumed immediately and goes into the grid for later use is charged for storage.

 

How can I best add this extra fee to the financial analysis?

Posted

Hi Tony,

this is not possible with net-metering. But maybe it is an option for you to export the simulation results and use the columns Grid Feed-in and Energy from Grid to calculate this balance by yourself?

Kind regards,
Frederik

 

Posted

Hi developer_fw,

I guess I will have to do it manually and add it to the report, but it would be great to add the funcionality.

From my knowledge, electricity distribution and transit fees are common in most countries, and it will be difficult to optimize the system when calculating the cost manually.

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.
Note: Your post will require moderator approval before it will be visible.

Guest
Unfortunately, your content contains terms that we do not allow. Please edit your content to remove the highlighted words below.
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

×
×
  • Create New...