August 15, 20224 yr comment_8321 Hi, I have a question regarding this theme. The total power of my 3D design is 82,68 kWp, which means according to my feed-in tariff I'll get 0,0474 €/kWh. And I also set my own grid tariff for 0,2 €/kWh. But why do I get 0,00 % of my IRR, although I have 72.518 kWh/Jahr of surplus supply to the grid? Report
August 18, 20224 yr comment_8372 Dear Zahra, the tariff is fine, I guess there is something wrong with the other parameters of the financial calculation. Could you provide the project file, please? You can send it to me here in the forum via private message. Kind regards, Martin Report
August 18, 20224 yr Author comment_8377 Hi Martin, thank you for your reply! I just realized that there was a mistake with the total amount of energy consumtion. But the problem is solved now, thank you! Report