Hello. can i have some guidance on how to input export limitation on a design and how to know its reading right on a report. my design has an install a generation capacity of 170kW, but the export has to be limited to 40kW. I've added the 40kw on the AC main options to set the limitation, but on the report its still showing a lot of export back to the grid.
i would assume it would only be showing the 40kw going back into the grid but in kwh?
Lyon Leisure Limited PV Report Option 1 Rev E.pdf