Hello, I'm new to the forum.
We have a site that has exiting solar with an export agreement (50kW DC) with 50kW AC inverters with 50kW export.
The DNO have approved another 50kW of AC, which will will oversize to circa 65kW DC, with a total site export of 50kW (not increased)
I have historic HH export and import data, but I can't find a way to load the export data into the modelling.
I have tried using negative numbers on the import data - but PVSOL doesn't like negative values here.
Any solutions?